Project Details

Location

White, GA

Square Feet

1,000,000

Duration

1 year

Toyo Tire

Provided design and construction of all electrical systems for a new auto tire manufacturing facility including (1) 1200A 12,470V services, (6) 2500KVA Unit substations, power monitoring system, All high output interior fluorescent lighting, exterior lighting, fire alarm system, structured cabling system, CCTV system, Access control system, and paging system. M&L has continued to work directly for Toyo Tire installing (14) mixing lines, (197) Cure Press machines, and (3) finishing areas that include tire uniformity machines, dynamic balancers, x-ray machine, auto trimmers and labeling carousels.